Day 19: Snow Delays...
Delayed a week after a couple snow storms... but it's melting now and this week we are ready for more concrete, then finally framing!
Monday, February 10, 2014
Day 14: Basement Prep and Wood
In the past couple of days, metal beams were placed under the garage, basement floor is being prepared for the concrete and piles of wood came in to start framing the house.
![](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEjfOx5uCeAgNAEARxBiEHRyWuo6ZwnwHMz_4jeMulJWtYfq-u7nGaa8KYtCLPQG4rtVD509Wc7cbRyZ-ZltpAM14PYVxNJ2GVdz1h-oq6m65E86q2L0S5ZHBPYywWu1KUDUV6bbB7tkjYg/s400/blogger-image--1423640222.jpg)
Thursday, February 6, 2014
Tuesday, February 4, 2014
Day 8: Plumbing and Waterproofing
Plumbing is in and basement walls were coated with waterproofing paint to keep rooms at normal humidity.