Friday, February 28, 2014

Day 31: Roof and Shingles

Roof and shingles installed. Also, the yard and driveway have been leveled and cleaned up. Looking good!

Thursday, February 27, 2014

Day 30: Framing Complete!

Amazing how much they can do in one day!

Late afternoon:

Early morning:

Tuesday, February 25, 2014

Day 28: Framing the Interior

They did a lot of work inside the house today. I see our stairs and windows have been installed.

Thursday, February 20, 2014

Day 23: Ready to Frame!

Foundation is complete and main level floor is done. Framing the house starts tomorrow!


Monday, February 17, 2014

Sunday, February 16, 2014

Day 19: Snow Delays...

Delayed a week after a couple snow storms... but it's melting now and this week we are ready for more concrete, then finally framing!

Monday, February 10, 2014

Day 14: Basement Prep and Wood

In the past couple of days, metal beams were placed under the garage, basement floor is being prepared for the concrete and piles of wood came in to start framing the house. 


Thursday, February 6, 2014

Tuesday, February 4, 2014

Day 8: Plumbing and Waterproofing

Plumbing is in and basement walls were coated with waterproofing paint to keep rooms at normal humidity.


Sunday, February 2, 2014

Day 6: Basement Walls

We have walls! Solid basement walls were up by the first weekend.. they are moving fast!