It's been a busy week at the house, we walked into a cozy, heated (almost) home today with a fresh coat of paint on all the walls. We also have all the lights including the outdoor floodlights, outlets, security system and doorbell powered on. Vinyl in the kitchen, morning room, laundry room and bathrooms, and base moldings have all been installed.
Monday, March 31, 2014
Saturday, March 22, 2014
Day 53: Cabinets
In love with the kitchen cabinets color, cherry java. It is the darkest color they offer that is real wood, not veneer. Also, fingerprintless.
Can't wait to start cooking and baking in here!
Kitchen:
Honey oak for the basement wet bar. This will look great with the black countertop.
Friday, March 21, 2014
Day 52: Stones Complete
Looks beautiful! Just waiting for the shutters on the middle/foyer window and for the front door to be painted and the exterior will be complete.
Thursday, March 20, 2014
Wednesday, March 19, 2014
Tuesday, March 18, 2014
Sunday, March 16, 2014
Saturday, March 15, 2014
Thursday, March 13, 2014
Day 44: Pre-Dry Wall Meeting
All inspections passed today, insulation has been installed and we are ready for dry wall!
Wednesday, March 12, 2014
Day 43: Plumbing, Wiring and More..
Lots of things installed inside the house within the last few days.
Saturday, March 1, 2014
Day 32: First-Time Inside the House