Thursday, February 20, 2014

Day 23: Ready to Frame!

Foundation is complete and main level floor is done. Framing the house starts tomorrow!


Monday, February 17, 2014

Sunday, February 16, 2014

Day 19: Snow Delays...

Delayed a week after a couple snow storms... but it's melting now and this week we are ready for more concrete, then finally framing!

Monday, February 10, 2014

Day 14: Basement Prep and Wood

In the past couple of days, metal beams were placed under the garage, basement floor is being prepared for the concrete and piles of wood came in to start framing the house. 


Thursday, February 6, 2014

Tuesday, February 4, 2014

Day 8: Plumbing and Waterproofing

Plumbing is in and basement walls were coated with waterproofing paint to keep rooms at normal humidity.


Sunday, February 2, 2014

Day 6: Basement Walls

We have walls! Solid basement walls were up by the first weekend.. they are moving fast!